My schedule would be the following:
Inventory- 24 hours (3x8 hours) in the warehouse of Abrunheira, then 8 hours in the warehouse of Povoa de São Adrião, total 32 hours.
Processing the
collected data - to be defined
Presenting and
discussion with the supervisor – 10 hours (2x5 hours)
Total
estimated working time: 42 hours
Although this project is still pending approval from CAS Coordinator.